County CouncilWednesday, November 18
Spartanburg County Council gives final approval to three data center agreements and advances three more
The Daily Spartanburg team
If you missed Monday night's meeting, here's the short version: Spartanburg County Council gave final approval to three data center agreements and advanced three more, with residents packing the room on both sides. The Valara Holdings project on South Pine Street passed 3-2, with Monier Abusaft and Grant DeShields opposed. The other two passed unanimously.
Three data center agreements won final approval Monday
| Project | Size | Agreement term |
|---|---|---|
| Valara Holdings, South Pine St. | 457 megawatts | 10 years |
| AIB CLT1 | 50 megawatts | 12 years |
| 300 Jones Road Associates | 65 megawatts | 5 years |
Sources: WYFF, South Carolina Public Radio
Three more AIB Data Centers proposals at Tyger River Industrial Park North in Moore passed first reading unanimously and need two more readings. The county's moratorium exempts some projects of 65 megawatts or less, and the agreements say the new ones qualify.
Valara's $2.75 billion tops six data center investments
Sources: WYFF, South Carolina Public Radio
View as table
| Value | |
|---|---|
| Valara | $2.75 billion |
| AIB CLT2 | $2.7 billion |
| AIB CLT3 | $2 billion |
| AIB CLT4 | $2 billion |
| 300 Jones Rd. | $1.5 billion |
| AIB CLT1 | $1.2 billion |
- Valara jobs: 27 full-time, per the developer
- Community benefit payments: could total $60 million for five projects
- Tax benefits council members cited: an additional $100 million
- Moratorium: expires in about 10 months
Opponents cited noise, pollution and water supply and rising utility costs. The Southern Environmental Law Center's Carl Brzorad said the county "is tying its own hands." Supporters pointed to investment and jobs.
Sources: WYFF, South Carolina Public Radio, FOX Carolina News, Here Greer